8.

Commissioning

8.1
Step 1 – Apply the voltage
After applying the voltage: LED 1 (Device) flashes green when the power supply is correct
8.2
Step 2 – Connection to the web server
Connect DEHNrecord SD directly to computer:
1. Configure computer: IP 169.254.0.1, Sub. 255.255.255.0
2. Connect computer and DEHNrecord SD directly with network cable
3. Activate web server: press push button 2 (Basic) briefly,
LED 1 (Device) lights up blue
4. Access with browser:
Password in delivery state:
8.3
Step 3 – Check
After successful login, the following properties can be checked and settings can be made, for example:
Rotation field direction of the voltage connections, connection of the current sensors, connection of the impulse current sensor.
LED 2 (Status) lights up green when the power quality is good (in factory configuration)