On-Grid Commissioning Of The Inverter - SolarEdge Se K Series Installation Manual

Three phase inverter with synergy technology
Hide thumbs Also See for Se K Series:
Table of Contents

Advertisement

On-grid Commissioning of the inverter

Step 1: Activating the Installation
During system activation, a Wi-Fi connection is created between the mobile device and
the inverter and the system firmware is upgraded.
Before activation
Download, register (first time only) and login to SetApp on your mobile device.
Verify that the application is updated with the latest version.
If applicable, turn on all devices (battery, Energy Meter) connected to the inverter,
so that the devices may be auto-detected.
To activate the inverter:
 1. Turn ON the AC circuit breaker on the main distribution panel.
 2. Open SetApp and follow the on-screen instructions (scan the inverter barcode;
move the ON/OFF/P switch to P position for 2 seconds and release).
SetApp creates a Wi-Fi connection, upgrades the inverter firmware and activates the
inverter.
 3. When the activation is complete, do one of the following:
Select Connect to Another Device to continue activating additional inverters.
Select Start Commissioning for pairing and other system configuration.
Step 2: Commissioning and Configuring the Installation
This section describes how to use the SetApp menus for commissioning and
configuring the inverter settings.
Menus may vary in your application depending on your system type.
To access the Commissioning screen:
Do one of the following:
During first time installation: Upon activation completion, in the SetApp, tap Start
Commissioning.
If the inverter has already been activated and commissioned:
If not already ON - turn ON AC to the inverter by turning ON the circuit breaker
on the main distribution panel.
Open SetApp and follow the on-screen instructions (scan the inverter QR code,
move the ON/OFF/P switch to P position for 2 seconds and release).
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx
Chapter 5: Activating, Commissioning and Configuring the System
    46

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Se17kSe20kSe100kSe7kSe10kSe8k ... Show all

Table of Contents