  Connecting Ground and AC to the Synergy Manager
Connecting Protective Earth (PE)
WARNING!
Turn OFF the AC before connecting the AC terminals. When connecting
equipment Grounding wire, connect it before connecting the AC Line and
Neutral wires.
To connect Protective Earth (PE) to the Synergy Manager:
1. Turn OFF and secure the main AC circuit breaker in OFF position at the circuit
breakers panel.
Release the six Allen screws and carefully remove the cover of the Synergy Manager.
2.
CAUTION!
When removing the cover, make sure not to damage internal components.
SolarEdge will not be held responsible for any components damaged as a
result of incautious cover removal.
3. Open the AC cable gland and insert the cable through the AC gland.
4. Expose 10 - 11 mm of the PE wire insulation.
5. Connect the PE wire to the PE terminal and fasten the Allen screw with a torque of
15 N*m.
NOTE
When using a stranded wire, use of ferrule is at the installer discretion.
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx
Figure 21: Connecting of PE (grounding) wire