R640 Equipment Installation
Installation of the equipment in the cabinet
Install equipment in the cabinet or rack. Always begin component installation at the bottom of the cabinet and work
upward. Install components at the lowest available space for that component type.
Placement of the equipment in the cabinet is dependent on the type of power distribution units installed in the cabinet.
Refer to the equipment stack up guidelines for each type of power distribution.
Install the servers as described in the following sections. Most of the servers will function as VxFlex Ready
l
Node nodes, and at least one will function as a management server. The procedures for physical installation in
the rack or cabinet apply to both types. Once the servers have been installed, refer to the VxFlex Ready Node
Hardware Configuration and Operating System Installation Guide (for your system's operating system), for server
configuration and operating system installation procedures.
Install the management switches
l
Install the data switches
l
Installation in cabinets with single-phase power distribution
Note:
Install all the equipment in the cabinet before installing and connecting the
power and I/O cables.
Install the equipment as described in
l
cabinet
on page
If you are installing the minimum configuration, refer to the figure and table
l
below for minimum configurations for the equipment stack up in the cabinet.
If you are installing the maximum configuration, refer to the figure and table
l
below for maximum configurations for the equipment stack up in the cabinet.
Table 2 Minimum configuration in single-phase power distribution cabinets
Component Function
Data Server
Management Server
Management Switch
Data Switch
Dell EMC VxFlex Ready Node Server Installation Guide
20
Installation of the equipment in the
20.
Description
R640 Server
Management Server
Customer provided 1 GbE
switch
Customer provided 10 GbE
switch
Quantity
3
1
1
2
Cabinet U Space
2 - 4
18
19
21 - 22