Installation In Cabinets With 3-Phase Wye Power Distribution; Minimum Configuration In 3-Phase Wye Power Distribution Cabinets - Dell EMC VxFlex Ready Node Installation Manual

Hide thumbs Also See for EMC VxFlex Ready Node:
Table of Contents

Advertisement

Installation in cabinets with 3-phase wye power distribution

Note:
Install all the equipment in the cabinet before installing and connecting the
power and I/O cables.
Install the equipment as described in
l
cabinet
on page
If you are installing the minimum configuration, refer to the figure and table
l
below for minimum configurations for the equipment stack up in the cabinet.
If you are installing the maximum configuration, refer to the figure and table
l
below for maximum configurations for the equipment stack up in the cabinet.
Table 6 Minimum configuration in 3-phase wye power distribution cabinets
Component Function
Data Server
Management Server
Management Switch
Data Switch
Installation of the equipment in the
20.
Description
R640 Server
Management Server
Customer provided 1 GbE
switch
Customer provided 10 GbE
switch
Quantity
3
1
1
2
Dell EMC VxFlex Ready Node Server Installation Guide
R640 Equipment Installation
Cabinet U Space
2 - 4
20
21
23-24
27

Advertisement

Table of Contents
loading

This manual is also suitable for:

Emc vxflex ready node r640Emc vxflex ready node r740xd

Table of Contents