R840 Equipment Installation
Figure 45 Installing the strain relief bar
3.
Route cables to the server, and thread hook-and-loop straps through the slits on the SRB.
If the system will be serviced in the rack, create cable service loops close to the SRB.
4.
Run the hook-and-loop straps around the cables to secure the cable bundles. Bundle the cables gently, ensuring
that you leave enough space for the cables to move when you slide the system out of the rack.
Figure 46 Using hook-and-loop straps to secure cables