VGE MultiMax Pro Installation & User Manual page 37

Uv-c sterilizer
Table of Contents

Advertisement

- Never position sampling points on an irradiation chamber, the sampling connections must be outside the
range of UV radiation. For this, the above-mentioned radiation depth can be used as a distance;
- When mounting the irradiation chamber, ensure that sufficient space is available around it for replacing
quartz tubes and UV lamps and for safely performing maintenance and service work;
- For an ideal hydraulic installation, a straight pipe length of 7 x the pipe diameter before the irradiation
chamber and 5 x the pipe diameter after the irradiation chamber is recommended;
- If you want to install 90° bends directly before and/or after the irradiation chamber, it is advisable not to
choose a bend radius smaller than 1.5 x the pipe diameter;
- During the installation of the irradiation chamber, ensure that no objects remain in the pipes or irradiation
chamber that could damage the UV system when starting the flow;
- After mounting the pipe, fill the irradiation chamber slowly to prevent damage due to water hammer;
- Before mounting the lamp and putting the UV system into operation, check the system for leaks and
repair it before putting it into operation;
- After installation of the pipes and irradiation chamber, it is recommended to clean the entire hydraulic
system before commissioning.
VGE International B.V.
Ekkersrijt 4304
 +31 499 461099
5692 DH Son Netherlands
Installation & User Manual
info@vgebv.nl
www.vgebv.nl
VGEM000-GB192
Pag. 37/68

Advertisement

Table of Contents
loading

This manual is also suitable for:

935mm0400

Table of Contents