Table of Contents TWIN-WALL PC PACKAGE: READ THIS BEFORE YOU Important Information ..........3 BEGIN End Panel Installation ..........5 Shelter Care and Maintenance ........9 The twin-wall PC package is designed to attach to either Quick Start Guide .............10 the R030B00001 end frame for the 30' wide roll-form, Polycarbonate Panels - 30' Wide ......11 or the R035B00001 end frame for the 35' wide roll-form Polycarbonate Panels - 35' Wide ......12...
INSTALL THE END PANEL POLYCARBONATE KIT. The following list identifies the main tools needed to assemble the end wall. Additional tools and supports may Thank you for purchasing this ClearSpan™ Twin-Wall be needed depending on the structure, location, and Polycarbonate Kit. When properly assembled and application.
Page 4
Important Information ASSEMBLY PROCEDURE PARTS IDENTIFICATION Following the instructions as presented will help ensure The following graphics and photos will help you identify the proper installation of the polycarbonate panels. The the different hardware used for the installation of the end steps outlining the assembly process are as follows: panel.
End Panel Installation Install panel cells vertically to allow condensation to drain END PANEL INSTALLATION from the cells. Consult the polycarbonate panels diagrams The steps that follow describe one way to complete the located in the Quick Start section for panel locations and polycarbonate panel installation.
Page 6
End Panel Installation END PANEL INSTALLATION (continued) Brace Locate and mark the center of the end wall and set the first prepared panel, with the UV-protected side facing to the outside, in position. Align the center of the H-channel with the center of the end frame. Tek screws ATTENTION: Consult the diagram in the Quick Start Tek screw...
Page 7
End Panel Installation END PANEL INSTALLATION (continued) Measure between the side H-channel sections of the center Upper panel (or panels) and cut H-channel to length. See diagrams Panel for panel size. Install H-channel along the top of the installed lower panel (or panels).
Page 8
End Panel Installation END PANEL INSTALLATION (continued) Repeat steps to install the next panel. Work from the center outward to install the remaining panels. Outer End Wall Panel 35' wide: The center, upper panels include H-channel installed on both sides and along the bottom edge. The bottom H-channel is common between upper and lower panels and connects the two panels.
Shelter Care and Maintenance SHELTER CARE AND MAINTENANCE Proper care and maintenance of the end panels is Space below is reserved for customer notes. important. Check the following items periodically to properly maintain the end panels: • Regularly check the polycarbonate panels to see that these are secure and in good condition.
Install Tek screws and washers through the panel and into the end wall brace. Panel Kit for 30' Evenly space the Wide Frame screws at 12". R030B00008 4' x 8' 4' x 8' 6' x 8' 6' x 8' Panel Panel Panel...