Installation and connection

7
Installation and connection
7.1 Requirements for the place of in-
stallation
The Wood lathe must be placed securely on a level and
firm surface. It must be ensured that there is sufficient
freedom of movement for working. The installation site
should meet the following criteria:
- The surface must be level, firm and free of vibrati-
ons.
- The substrate must not allow any lubricants to pass
through.
- The installation or work area must be dry and well
ventilated.
- No machines causing dust or chips should be opera-
ted near the machine.
- There must be sufficient space for the operating per-
sonnel, for material transport and for adjustment and
maintenance work.
- The place of installation must have good lighting.

7.2 Setting up the lathe

CAUTION!
Risk of injury from an unstable machine!
Check the stability of the machine after setting it up
on stable ground.
CAUTION!
Observe the weight of the machine!
The machine may only be set up by two persons
together.
Check the appropriate aids for adequate dimensio-
ning and load capacity.
ATTENTION!
In order to ensure sufficient stability of the machine, it
should be bolted to the ground. For this purpose there
are 4 holes at the bottom of the machine frame.
The lathe is supplied in a wooden box and is already lar-
gely assembled. Only a few parts have to be assembled
after delivery.
10
8

Mounting

ATTENTION!
During assembly, the parts must first be loosely
screwed together. When all parts are assembled,
align the parts at right angles before tightening the
screws.

8.1 Model DB 900

8.1.1Assembly of the machine frame
Fig. 5: Assembly of the machine frame
The machine frame is prepared for operation with the
following steps:
Step 1: Screw the frame feet (Pos.1, Fig.5) to the bracket
(Pos.2, Fig.5) using 3 M8x12 round head
screws (Pos.3, Fig.5) and the corresponding
washers (Pos.4, Fig.5) and nuts (Pos.5, Fig.5).
Step 2: Attach the tool rest to the intended position
(Pos.6, Fig.5) with a total of 8 M8x12 round
head screws, washers and nuts.
8.1.2Assembly of the machine bed
2
1
Fig. 6: Assembly of the machine bed
Place the machine frame on a level work surface.
Lift the machine onto the machine frame with the aid of a
second person. Fasten it with 8 M8x35 hexagon socket
screws (Pos.1, Fig. 6). Place a spring washer under
each nut.
The machine bed extension (Pos.2, Fig.6) must also be
mounted. Tighten it with two hexagon socket screws
M10x25 and spring washers.