INSTRUCTIONS 360 Y-DROP ® APACHE 360 Y-DROP REGISTRATION ® Please visit productregistration.360yieldcenter.com to complete the product registration for your 360 Y-DROP so we can better support our products from day one and ensure you have the latest upgrades, warranty parts and technical support. Thank you! 360YIELDCENTER.COM V1 - 11.30.2016...
INSTRUCTIONS 360 Y-DROP APACHE INTRODUCTION Before beginning, it’s important to know where each mounting bracket fits relative to the row spacing involved. The 360 Y-DROP unit should be precisely centered on the machine, as this is critical to the assembly of the system to the sprayer and for mounting the system to your sprayer boom.
Page 3
INSTRUCTIONS 360 Y-DROP APACHE ESTABLISH DROP LOCATIONS Figure 1 Step 1 Locate the center of the machine and identify the location of all the drops. On the sprayer boom, mark where each riser mount will be located. This will ensure that the extension tubes will not interfere Figure 1 with the riser mounts.
Page 4
INSTRUCTIONS 360 Y-DROP APACHE INSTALL MOUNT ASSEMBLIES ON THE OEM PRIMARY BOOM Figure 3 Step 1 With the threads pointing down, install U-bolt (1) on the top of the OEM primary boom. Bag AF Step 2 Install bracket assembly (2) and flange Figure 3 lock nut (3).
Page 5
INSTRUCTIONS 360 Y-DROP APACHE INSTALL MOUNT ASSEMBLIES ON THE OEM PRIMARY BOOM (CONTINUED) Figure 6 Step 7 With the U-bolt pointing to the rear, install the yoke mount (1) and flange nuts to upper boom section. Step 8 With the square U-bolt threads pointing up and using the extra thick washer and Nylock nut, install yoke mount (2) to the 360 Y-DROP boom section.
Page 6
INSTRUCTIONS 360 Y-DROP APACHE INSTALL CENTER SECTION III. SQUARE TUBE Figure 7 Step 1 Install u-bolt (1) and 14" top plate (2) using the supplied hardware. Step 2 Install bracket assemblies (3). Figure 8 Step 3 Install extension tube (1). Figure 7 Step 4 Install 360 Y-DROP boom bracket (2)
Page 7
INSTRUCTIONS 360 Y-DROP APACHE INSTALL 360 Y-DROP BOOM Figure 10 Step 1 Assemble 5' boom sections (1) using the 8" boom connectors (2) and the supplied hardware. Hardware Bag CC Step 2 Repeat Step 1 as needed in order to Figure 10 assemble the entire 360 Y-DROP boom.
Page 8
INSTRUCTIONS 360 Y-DROP APACHE INSTALL BREAKAWAY ASSEMBLY - ONE PIECE Figure 14 Step 1 Install breakaway assembly - one piece (1) using the square U-bolts (2) and the extra thick washer and Nylock nut. Repeat for the remaining breakaway assemblies - one piece.
Page 9
INSTRUCTIONS 360 Y-DROP APACHE INSTALL RISER MOUNTS WITHOUT BREAKAWAY ASSEMBLIES (OPTIONAL) Figure 16 Step 1 Install riser mount (1) using the square U-bolts (2) and the extra thick washer and Nylock nut. Repeat for the remaining riser mounts. Hardware Kit C Figure 16 NOTE: The alignment and quantity of the riser mounts will depend on your row spacing.
Page 10
INSTRUCTIONS 360 Y-DROP APACHE INSTALL SHIELDS AND RISER HOSES Figure 18 Step 1 Install shield (1) onto riser tube (2). Figure 19 Step 2 Install base unit (1) onto riser tube (2). Figure 20 Step 3 Assemble drag hoses (1) to 360 Y-DROP Figure 18 base and secure with hose clamps (2).