Installation - ESAB OrigoArc 150 Service Manual

Table of Contents

Advertisement

INSTALLATION

The installation must be executed by a professional.
WARNING!
This product is intended for industrial use. In a domestic environment this product may cause radio
interference. It is the user's responsibility to take adequate precautions.
Placing
Place the welding power source so that its cooling air inlets and outlets are not obstructed.
Rating plate
The rating plate is located on the underside of the power source.
Mains power supply
Make sure that the welding power source is connected to the correct supply voltage and
that it is protected by the correct fuse rating. The standards for the country in question must
be complied with as regards the mains cable area. A protective earth connection must be
made in accordance with regulations.
Recommended fuse ratings and minimum cable areas
Mains voltage
Mains frequency
Fuse (delayed- -action)
85A 35% duty cycle
120A 20% duty cycle
150A 25% duty cycle
Mains cable area
Welding cable area
*) Note:
The installed mains cable plug is approved for maximum 16 A.
Australian version: The mains cable plug is approved for maximun 15 A.
The cable area and fuse rating above comply with Swedish regulations. Use the welding power source
in accordance with the relevant national regulations.
ch25ie1
230 V ¦10 %, 1--phase
50 -- 60 Hz
10 A
16 A
20 A*)
2
3 x 2.5 mm
2
16 mm
- - 25 - -
Edition 040830