2.11

Prerequisites for this Procedure

In order to perform this procedure, you will need the following information:
1) The location code of the FRU to be serviced
2) The cage location of the FRU to be serviced
3) The frame number of the FRU to be serviced
2.12

Overview of Procedure

This is an overview of the tasks to be performed. Read this overview but do not perform any of the tasks yet.
PREPARE CEC DRAWER FOR SERVICE TO SLIDES/RAILS
HAVE CUSTOMER CHECK FOR GPFS NODE AND SHUTDOWN CEC DRAWER
START FRU REPLACEMENT PROCEDURE
FRONT MECHANICAL PREPARATIONS FOR CEC SLIDES/RAILS SERVICE
ATTACH LIFT TOOL TO RACK
REAR MECHANICAL PREPARATIONS FOR CEC SLIDES/RAILS SERVICE
TEMPORARILY REMOVE CEC DRAWER
RE-INSTALL CEC DRAWER TO ORIGINAL POSITION
VERIFY ALL D-LINKS AND L-LINKS ARE OPERATIONAL
CONFIRM WITH CUSTOMER THAT CEC IS OPERATIONAL
Power775 CEC Drawer Rails Service Procedure
PN: 41U8495, EC N44172
Page 11 of 42