Section 5 ·
Installati on and Start-Up

5.8 Starting up the inverter

After completing the mechanical and electrical installation, the inverter is put into operation as follows:
NOT E
The inverter can be put into operation only under daylight
conditions (i.e. at a solar generator voltage of > 100 V).
If no daylight or solar generator voltage is present, the
inverter can be activated by pressing the night start key if
there is AC voltage present (see section 4.4 in the Operating
Instructions). However, normal operation is not possible in
this condition. Only the values can be read off the display.
A CTI ON
Switch on the line voltage and the solar generator with the
aid of the AC/DC disconnect switch (O → I).
During the initial start-up, the corresponding country and language must be selected. Select the appropriate language using the '2'
(right) key, press the '1' (left) key to advance to the country selection. Press the '2' key to advance through the various grid types. Once
the proper grid type is selected press the '1' key then press both the '1' and '2' keys at the same time to save the settings. If the improper
grid settings were selected, hold down the '2' key to start the process again.
NOTE
If the power is cycled or 10 minutes elapse the settings for
the grid type are locked and a password will need to be
obtained from tech support.
The top green LED "OK" lights when DC voltage is available and indicates that it is ready to be put into operation. The display now
indicates the current PV generator voltage "Start from xx V, meas.: xxx V". If the measured voltage is greater than the starting voltage,
the unit will start grid-feeding after a country-specific waiting time. This start-up waiting period is required in order to ensure that the
generator voltage is continuously above the power delivery limit of 125 V (1502xi) and 200 V (2502xi, 3502xi and 5002xi).
A quick start routine is provided for startup and test purposes. This routine circumvents the start-up delay period. This quick start routine
is found in the configuration mode menu (see Operating Instructions).
During the normal start-up procedure, the line relays audibly switch on after a country-specific waiting time and the feeding of the grid
starts. This is indicated by the middle green LED with the house and power line symbol next to it. The display now shows the power
being fed into the grid. Key '1' (left) can now be used to display the various measured values (see Operating Instructions section 4.4).
blueplanet Operating and Installation Instructions 1502xi - 5002xi
31000770-02-112609