Preparing For Operation; Download Modified Project To The; Pnozmulti Safety System; Connection - Pilz PNOZmulti PNOZ m EF 8DI4DO Operating Manual

Hide thumbs Also See for PNOZmulti PNOZ m EF 8DI4DO:
Table of Contents

Advertisement

6
Commissioning
6.2

Preparing for operation

6.2.1
Download modified project to the PNOZmulti safety system
6-
Preparing for operation
6200
Preparing for operation
6.2
6- Verdrahtung_multi_Modul_Betr_geaend_Projekt_BA
Download modified project to the PNOZmulti safety system
6.2.2

Connection

Connection
6- Betriebsbereitschaft herstellen
Supply voltage
Supply voltage
Connection examples for the input circuit
Input circuit
Example:
E-STOP
without detection of shorts across
contacts
Example:
E-STOP
with detection of shorts across con-
tacts
6-2
As soon as an additional expansion module has been connected to the
system, the project must be amended using the PNOZmulti Configura-
tor. Proceed as described in the operating instructions for the base unit.
NOTICE
For the commissioning and after every program change, you
must check whether the safety devices are functioning correctly.
DC
Single-channel
Dual-channel

Advertisement

Table of Contents
loading

Table of Contents