Commissioning
5.1
Overview
Prerequisites
1. The device has been installed.
2. The device has been connected in accordance with the possible connection methods.
3. The RS485 interface has been connected to the bus.
Note: The RS485 interface must be connected for commissioning via the powerconfig
parameterization software.
Steps for commissioning the device
1. Connect the supply voltage.
2. Parameterize the device.
3. Connect the measuring voltage.
4. Check the displayed measured values for plausibility.
5. Check the polarity and the phase assignment of the instrument transformers.
NOTICE
Device can be irreparably damaged
When performing an insulation test of the entire installation with AC or DC, the device
should be disconnected before starting the test.
Note
Check the connections.
Incorrect connection can result in malfunctions and failure of the device.
Prior to commissioning the power monitoring device, check that all connections are correct.
PAC1020
Equipment Manual, 05/2020, L1V30610008B-01