Verifying The Installation - Huawei UPS5000-S-1200 Quick Manual

Hide thumbs Also See for UPS5000-S-1200:

Advertisement

4

Verifying the Installation

1. Check that there is no foreign matter in the cabinets.
2. (Remove the paper protective film from the sealing putty.) After routing cables and
verifying cable connections, seal the gap between cables and the cabinet using sealing putty.
Sealing putty must be used as a whole and
the gap can be sealed only from the top.
3. After verifying the installation, reinstall all the covers.
4. Do not remove the dustproof cover before power-on to prevent dust from entering the UPS.
5
Powering On and Starting the UPS
1. Before powering on the UPS, ensure that the UPS has passed all check items in the
Commissioning and Acceptance Report
2. Measure the voltage and frequency of the mains and bypass inputs of the UPS, or the
voltage and frequency output from the external input power distribution cabinet (PDC) to
the UPS. Ensure that the line voltage is in the range of 138–485 V AC and the frequency is in
the range of 40–70 Hz.
5.1
Powering On the UPS
Turn on mains input circuit breaker Q1-1, Q1-2 and bypass input switch Q2.
After the UPS is powered on, initialization begins. The monitoring display unit (MDU)
Paper
protective
film
Turn on the upstream bypass and mains input switches
Turn on SPD switch 1QFS and 2QFS.
Turn on output circuit breaker Q5-1 and Q5-2.
displays the Huawei logo and an initialization progress bar.
Sealing putty
and Chapter 4.
15
UPS5000