Summary of Contents for Huawei SmartLi-512V-80AHF-01
Page 1
2. Use insulated tools during installation and operation. 3. Only Huawei engineers or engineers certified by Huawei are allowed to install, commission, and maintain the battery cabinet. Otherwise, personal injury or equipment damage may occur, and the resulting battery cabinet faults are beyond the warranty scope of Huawei.
Page 2
Installing a Fire Cylinder 1. Remove the rear panel of the cabinet. 2. Remove the fire cylinder. a) Remove the fire cylinder fastener. b) Take out the fire cylinder. 3. Check the fire cylinder and all components for any damage, abrasion, or corrosion. If there is any visible abrasion or corrosion, replace the damaged components and all corroded components.
Page 3
7. Install the fire-trace tube on the fire cylinder. b) Tighten the connection nut to 7 N· m using an adjustable torque wrench. Do not bend or twist the fire-trace tube or bind the tube using cable ties. Otherwise, the fire cylinder may fail.
Installing a Cabinet Secured Installation 3. Slide the cabinet on its castors to the 1. Determine the position for installing the installation position. cabinet. Mark mounting holes based on the 4. (Optional) If the castors of the SmartLi need drawings (unit: mm). to be lifted from the ground, perform Step 1 to Step 2 in Non-Secured Installation.
Page 5
Combining Cabinets 1. Install each cabinet in sequence according to the installation method of a single cabinet. 2. Combine cabinets.. 1. The SmartLi supports the combination of up to eight cabinets. 2. When multiple cabinets are connected in parallel, only the basic cabinet has an LCD.
Page 6
The cabling route is for reference only. Connect cables based on site requirements. Installing a Ground Cable 1. Remove the PDU and fuse cover. 2. Remove the cover from the top of the cabinet based on the cable route and cable dimensions.
Page 7
Installing Battery Modules and Cables 1. Pull out the battery monitor unit for about 10 cm. • Install the battery modules from bottom to top and from left to right to prevent falling over due to imbalance. • Two persons are required to install the battery modules.
Page 8
3. Remove front cover from the battery module, and install battery baffle plate. 4. Install battery communications cables. a. Install communications cables between battery modules. b. Connect communications cables (reserved in the cabinet) between the battery modules and the battery monitor unit . Full-capacity Cabinet Configuration Half-capacity Cabinet Configuration...
Page 9
5. Install battery copper bars and cables. a. Open the terminal protective covers, install copper bars between battery modules, and close the terminal protective covers. b. Open the terminal protective covers, install copper bars between battery modules and fuses, and close the terminal protective covers.
7. Reinstall the battery monitor unit . Installing Output Cables Connect power cables to the UPS. The following uses the UPS with a neutral wire as an example. With a BBB-BOX Without a BBB-BOX...
Page 11
Installing Communications Cables Connect a communications cable to the UPS. Single Cabinet Parallel System, for Example, Five Cabinets The numbers of cabinets in a parallel system depend on the connection of control cables. After the control cables are connected according to the preceding figure, the cabinets are numbered 1, 2, 3, 4, and 5 from top to bottom.
Verifying the Installation 1. Check that there is no foreign matter at the top 5. Do not remove the dustproof cover before and bottom of the cabinets, copper bars, power-on to prevent dust inside the SmartLi. switches, and the rear of units. Top dustproof cover 2.
Page 13
3. Set the language, time, date, network parameters, and system parameters on the Settings Wizard screen. System User LCD Preset Password WebUI Preset Password admin (system administrator) 000001 Changeme operator (common user) 000001 Changeme To ensure system security, change the LCD and WebUI passwords after the first login. Item LCD Preset Password Default Value...
4. After the green indicator of the battery monitor unit blinks at 10 Hz, turn on the battery circuit breaker on the SmartLi. 5. When multiple SmartLi cabinets are combined: 1) If the green indicator of one battery monitor unit blinks at 10 Hz, turn on the battery circuit breaker on any SmartLi.
Page 15
Scan here for technical support (carrier): Huawei App Store Scan here for more documents: Support-E Support WeChat You can also log in to Huawei technical support website: https://support.huawei.com/enterprise https://support.huawei.com Huawei Technologies Co., Ltd. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China...