    General Information 1.1 Overview Contents 1.2 Applicable Products 1.3 Warnings 2. Installation 2.1 Installation safety 2.2 Installation Condition 2.2.1 Climate condition 2.2.2 Site selection 2.2.3 Tilt angle selection 2.3 Mechanical Installation introduction 2.3.1 Fixation with screws 2.3.2 Fixation with clamps at long sides of frames 2.3.3 Fixation with clamps at short side of the frames Wiring and connection Maintenance and care...
  • Page 3: General Information

    1. General Information 1.1 Overview Thanks for choosing Jinko Solar PV modules. In order to ensure the PV modules to be installed correctly, please read the following operation instructions carefully before modules installed and used. Please remember that the products would generate electricity and certain safety measures need to be taken to avoid danger.
  • Page 4 JKMxxxP-72 (xxx=250-340, in steps of 5, 72 cells) JKMxxxP-72-J (xxx=250-340, in steps of 5, 72 cells) JKMxxxPP-72 (xxx=250-340, in steps of 5, 72 cells)*** JKMxxxPP-72-J (xxx=250-340, in steps of 5, 72 cells) JKMxxxP-72-J4 (xxx=250-340, in steps of 5, 72 cells)*** JKMxxxPP-72-J4 (xxx=250-340, in steps of 5, 72 cells) JKMxxxP-72(Plus) (xxx=250-340, in steps of 5, 72 cells) JKMxxxPP-72(Plus) (xxx=250-340, in steps of 5, 72 cells)
  • Page 5 JKMxxxM-96-J (xxx=210-285, in steps of 5, 96 cells) JKMxxxM-72-J (xxx=160-215, in steps of 5, 72 cells) JKMxxxM-96B (xxx=210-285 in steps of 5, 96 cells) JKMxxxM-72B (xxx=160-215, in steps of 5, 72 cells) JKMSxxxM-96 (xxx=210-285, in steps of 5, 96 cells) JKMSxxxM-72 (xxx=160-215, in steps of 5, 72 cells) JKMSxxxM-96-J (xxx=210-285, in steps of 5, 96 cells) JKMSxxxM-72-J (xxx=160-215, in steps of 5, 72 cells)
  • Page 6: Warnings

    1.3 Warnings  PV modules generate DC electrical energy when exposed to sunlight or other light sources. Active parts of module such as terminals can result in burns, sparks, and lethal shock.  Artificially concentrated sunlight shall not be directed on the module or panel. ·...
  • Page 7 Use insulated tools for electrical connection  Do not remove any part installed by Jinko Solar or disassemble the module.  All instructions should be read and understood before attempting to install, wire, operate and maintain the module.  Please don‟t lift up PV modules using the attached cables or the junction box. ...
  • Page 8: Installation

     Do not clean the glass with chemicals.  Do not disconnect any of the modules when it is under load. 2. Installation 2.1 Installation safety  ways wear protective head gear, insulating gloves and safety shoes (with rubber soles). ...
  • Page 9: Installation Condition

    2.2 Installation Condition 2.2.1 Climate condition Please install the modules in the following conditions: a) Operating temperature: within –40°C(-4℉) to 85°C (185℉) b) Relative humidity: within 45% to 95%. ﹡Note: The mechanical load bearing (include wind and snow loads) of the module is based on the mounting methods.
  • Page 10: Tilt Angle Selection

    generate hydrogen gas when charging, which can be explosive. Do not light matches or create sparks near the battery bank. When a battery is installed outdoors, it should be placed in an insulated and ventilated battery case specifically designed for the purpose.
  • Page 11: Fixation With Screws

    ﹡ Note: All installation methods herein are only for reference, and Jinko solar will not provide related mounting components, the system installer or trained professional personnel must be responsible for the PV system‟s design, installation, and mechanical load calculation and security of the system. 2) Before installing, you should confirm below important things: 1) Visual check before installation, to make sure there is no bug in the packing and junction box as well as the surface of module, If have , remove and clean...
  • Page 12 Figure 2: PV module installed with Screw fitting method Module type Cell type Cell Pmax Dimensions(mm) JKMXXXM-72 Module:1580*808 JKMXXXM-72-I 5 inch Mono 6*12 160~215Wp Frame: 35*25 & 35*35 & 40*30 & 40*35 JKMXXXM-72-J & 45*35 & 50*35 JKMXXXM-72B JKMXXXM-96 JKMXXXM-96-I Module:1575*1082 5 inch Mono 8*12 210~285Wp...
  • Page 13 JKMXXXP-60 JKMXXXP-60-I Module:1650*992 JKMXXXP-60-J Frame:40*30 & 40*35 & 45*35 & 50*35 JKMXXXPP-60 & 35*35 JKMXXXPP-60-J 6 inch Poly 6*10 210~280Wp JKMxxxP-60-J4 JKMxxxPP-60-J4 Module:1650*990 JKMxxxP-60(Plus) Frame: 40*35 JKMxxxPP-60(Plus) JKMXXXP-60B JKMXXXM-60 Module:1650*992 JKMXXXM-60-J 6 inch Mono 6*10 210~280Wp Frame:40*30 & 40*35 & 45*35 & 50*35 JKMxxxM-60-(Plus) &...
  • Page 14 JKMSXXXP-72 JKMSXXXP-72-J Module:1956*992 6 inch Poly 6*12 250~340 JKMSxxxP-72-J4 Frame: 40*30 & 40*35 & 50*35 JKMSxxxP-72(Plus) JKMSXXXM-72 Module:1956*992 JKMSXXXM-72-J 6 inch Mono 6*12 250~335 Frame: 40*30 & 40*35 & 50*35 JKMSxxxM-72(Plus) 6 inch Module:1956*992 JKMSXXXP-72L Quasi- 6*12 255~330 Frame: 40*30&50*35 Mono 6 inch Module:1650*992...
  • Page 15: Fixation With Clamps At Long Sides Of Frames

    2.3.2 Fixation with clamps at long sides of frames The applicable Products please refer to Table 2, and only allow using clamps at long side of frames. The module clamps should not come into contact with the front glass and must not deform the frame.
  • Page 16 Figure 3: PV module installed at long side with Clamp fitting method Dimension(mm) Cell Cell Pmax Module type type quantity (Wp) Frame 1580*804 300 400 30*20 & 35*25 & 40*20 JKMSXXXM-72 5 inch 30*20 & 35*25 & 35*35 6*12 160~215 JKMSXXXM-72-J Mono 1580*808...
  • Page 17 JKMXXXM-72 35*25 & 30*20 & 35*35 JKMXXXM-72-I 5 inch 6*12 160~215 1580*808 300 400 & 40*30 & 40*35 & JKMXXXM-72-J Mono 45*35 & 50*35 JKMXXXM-72B JKMXXXM-96 JKMXXXM-96-I 5 inch 40*20 & 40*30 & 40*35 8*12 210~285 1575*1082 280 400 JKMXXXM-96-J Mono &...
  • Page 18 JKMSxxxM-48-J 6 inch 170~220 1324*992 240 270 40*35 JKMSxxxM-48(Plus) Mono JKMxxxP-48 JKMxxxPP-48 6 inch JKMxxxPP-48-J4 170~225 1324*992 240 270 40*35 Poly JKMxxxPP-48-J JKMxxxPP-48(Plus) JKMSxxxP-48-J 6 inch JKMSxxxP-48-J4 170~225 1324*992 240 270 40*35 Poly JKMSxxxP-48(Plus) 5400Pa mechanical load Max. Pressure: Table 2: Mechanical dimensions when modules installed at long side with Clamp fitting method 2) Light PV module: - 16 -...
  • Page 19 Figure 4: Light PV module installed at long side with Clamp fitting method Dimension (mm*mm) 28*6.9 Longer Frame Section: Short Frame Section: 28*15 19*15 Beam Section: Dimension(mm) Cell Pmax Module type Cell type quantity (Wp) JKMXXXM-72 JKMXXXM-72-I 5 inch Mono 6*12 160~215 1580*808...
  • Page 20 JKMXXXM-60 JKMXXXM-60-J 6 inch Mono 6*10 210~280 1650*992 JKMxxxM-60-(Plus) JKMXXXM-60B JKMXXXP-72 JKMXXXP-72-J JKMXXXPP-72 JKMXXXPP-72-J 6 inch Poly 6*12 250~340 1956*992 JKMxxxP-72-J4 JKMxxxP-72(Plus) JKMXXXP-72B JKMXXXM-72 JKMXXXM-72-J 6 inch Mono 6*12 250~335 1956*992 JKMxxxM-72(Plus) JKMXXXM-72B JKMSXXXM-72 1580*804 5 inch Mono 6*12 160~215 JKMSXXXM-72-J 1580*808 1580*1060...
  • Page 21: Fixation With Clamps At Short Side Of The Frames

    2.3.3 Fixation with clamps at short side of the frames The applicable Products please refer to Table 4, only refer to the Normal PV module, and only allow using clamps at short side of frames. The considerations and requirements about mounted by using clamps, please refer to the instructions in 2.3.2, and find detailed mounting information in the below illustration, the mounting place distance is suggested bigger than J and less than K,...
  • Page 22 Dimension(mm) Cell Cell Pmax Module type type quantity (Wp) Frame JKMSXXXP-60 JKMSXXXP-60-J 6 inch 6*10 210~280 1650*992 40*35 JKMSxxxP-60-J4 Poly JKMSxxxP-60(Plus) JKMSXXXM-60 6 inch JKMSXXXM-60-J 6*10 210~280 1650*992 40*35 Mono JKMSxxxM-60(Plus) JKMSXXXP-72 JKMSXXXP-72-J 6 inch 6*12 250~335 1956*992 40*35 JKMSxxxP-72-J4 Poly JKMSxxxP-72(Plus) JKMSXXXM-72...
  • Page 23 JKMXXXM-60 JKMXXXM-60-J 6 inch 6*10 210~280 1650*992 40*35 JKMxxxM-60-(Plus) Mono JKMXXXM-60B JKMXXXP-72 JKMXXXP-72-J JKMXXXPP-72 6 inch JKMXXXPP-72-J 6*12 250~340 1956*992 40*35 Poly JKMSxxxP-72-J4 JKMSxxxP-72(Plus) JKMXXXP-72B JKMXXXM-72 JKMXXXM-72-J 6 inch 6*12 250~335 1956*992 40*35 JKMxxxM-72(Plus) Mono JKMXXXM-72B 6 inch JKMXXXP-60L 6*10 215~275 1650*992 40*35...
  • Page 24: Wiring And Connection

    3. Wiring and connection a) Before this procedure, please read the operation instructions of the PV system carefully. Make wiring by Multi-connecting cables between the PV modules in series or parallel connection, which is determined by user‟s configuration requirement for system power, current and voltage. b) PV module connected in series should have similar current.
  • Page 25 with local and national electrical codes. Attach the equipment grounding conductor to the module frame using the hole and hardware provided. Not that a stainless steel star washer is used between the ground wire and module frame (see picture below).This washer is used to avoid corrosion due to dissimilar metals. Tighten the screw securely.
  • Page 26: Maintenance And Care

    4. Maintenance and care It is required to perform regular inspection and maintenance of the modules, especially within warranty scope. To ensure optimum module performance, Jinko recommends the following maintenance measures: 4.1 Visual Inspection Inspect the Modules visually to find whether there are appearance defects, the following need to be paid more attention especially: a) Whether the glass is broken;...
  • Page 27: Inspection Of Connector And Cable

    1.25 when determining component voltage ratings, conductor current ratings, fuse sizes, and size of controls connected to the PV output. The corresponding electrical specification can be downloaded from website www.jinkosolar.com. - 25 -...
  • Page 28: Disclaimer Of Liability

    6. Disclaimer of Liability Because the use of the manual and the conditions or methods of installation, operation, use and maintenance of photovoltaic (PV) product are beyond Jinko‟s control, Jinko does not accept responsibility and expressly disclaims liability for loss ,damage, or expense arising out of or in any way connected with such installation, operation, use or maintenance.