Commissioning; Checking Before Power-On - Alpha ESS SMILE-S6-HV Installation Manual

Energy storage system (ess)
Hide thumbs Also See for SMILE-S6-HV:
Table of Contents

Advertisement

Your Smart Energy

9. Commissioning

9.1

Checking Before Power-On

No. Check Item
1
Mounting environment
Battery pack and
2
inverter mounting
3
WiFi mounting
4
Cable layout
5
Cable tie
6
Grounding
Switch and breakers
7
status
8
Cable connections
Unused power
9
terminals
___________________________________________________________________
Page 60 of 75
Acceptance Criteria
The mounting space is proper, and the mounting
environment is clean and tidy, without foreign object.
The battery pack and inverter are mounted correctly,
securely, and reliably.
The WiFi module is mounted correctly, securely, and
reliably.
Cables are routed properly as required by the
customer.
Cable ties are secured evenly and no burr exists.
The ground cable is connected correctly, securely,
and reliably.
The PV switch and battery breakers and all the
breakers connecting to the product are OFF.
The AC cable, PV cable, battery cable, and
communication cables are connected correctly,
securely, and reliably.
Unused power terminals are blocked by
watertight caps.