Inspecting The Unit Prior To Initial Start-Up - Mandik CPV Installation, Commissioning And Maintenance

Compact air handling units
Table of Contents

Advertisement

MANDÍK CPV Installation, commissioning, and maintenance

7.2 INSPECTING THE UNIT PRIOR TO INITIAL START-UP

LIST OF SERVICING OPERATIONS PRIOR COMMISSIONING AIR-CONDITIONING UNIT MANDÍK
Order number:
Date:
Project name:
Address:
Date of first start-up:
Opera
Description of servicing operation
tion
Check the seating order of the chambers within
1.01.
the unit acc. to the documentation.
Check each chamber for external or internal
1.02.
damage.
Check the seating of the unit – on the
1.03.
floor/ceiling acc. to installation instructions.
Check connecting eccentric pieces between the
1.04.
chambers – in the "tightened" position.
Check the tightness of chamber connections –
1.05.
visually, acc. to installation instructions.
Check the total tightness of the unit – visually
1.06.
(the door, service panels, fixed panels, etc.).
Check the mounting of the roof on outdoor
1.07.
units acc. to installation instructions.
Check the cleanness of the chamber interior –
1.08.
without foreign bodies and construction
Check closing of the unit – the door, service
1.09.
panels.
Check the connection of HVAC piping to the
1.10.
damping inserts acc. to installation
Check the legibility and cleanness of
1.11.
manufacturing and safety plates. Clean if
1.12.
1.13.
1.14.
1.15.
1.16.
1.17.
1.18.
1.19.
IZU 06/2021
OPERATIONS FOR THE UNIT IN GENERAL
Completion of operation
MANDÍK, a.s., www.mandik.cz
User:
Commissioning party:
Serial number:
Position:
Measured or set
value *
YES
NO
R
Comment
20