Entyce Lifting Instructions - Hussmann Entyce TY3 Series Installation & Operation Manual

Hide thumbs Also See for Entyce TY3 Series:
Table of Contents

Advertisement

Entyce Hot Lifting Instructions
1. The Entyce Hot can be lifted by a forklift underneath the base only at the specified location in the diagram with proper
lifting equipment.
2. Remove close offs and lower body panels before lifting case. Serious damage will occur if the body panels are not re-
moved.
• Remove the end case lower panels first if not done so already.
• A Phillips head screwdriver/drill is needed for lower and bottom panel removal
3. Make sure that fork spacing and width will not damage drain, piping, or electrical lines
4. The Entyce can be raised at one end with a forklift to allow the placement of rollers or dollies. See figure above on page
5 for J-bar and jacking instructions
5. Never drag or push the Entyce by ANY COMPONENT including ANY GLASS COMPONENT. This will result in dam-
age to the base, and possibly damage to other components
6. Evenly support the entire base structure on rollers or dollies before attempting to move. Each Base Leg must have its
own dollie to properly support the case.
WARNING
Improper placement of forks may damage
drainage piping. Use a spotter when placing forks.
Make sure that piping will not be damaged.
Use J-Bars or Jacks if Forks cannot be used safely
Dollies recommended
under each corner for
transit.
5

Advertisement

Table of Contents
loading

This manual is also suitable for:

Entyce ty4 seriesTy3-4-hTy3-4x4e-hTy3-4x5e-h

Table of Contents