Page 4
Product Parameter and Features • Capacity choice from 7.10 – 24.86kWh Force H1 - typical RESS & light commercial Force H2 - 3-Phase small RESS • Modular design, flexible on expansion • 35kG per module, light on weight stackable mounting, installation cost save •...
Page 10
Installation Checking List 1) For battery module package: 1*battery module.
Page 11
Installation Checking List 2) For BMS package: 1*BMS, 2*long metal bracket, 2*short metal bracket, 1*base, 2*power cable(3.5M), 2*communication cable(3.5M), 1*grounding cable(2M), screws, manual and warranty card.
Page 12
BEFORE YOU START • Installation Manual • Location & Environment • Tools & Accessories • Compatible Inverter...
Page 13
INSTALLATION 1) Installation of the base: >300mm above ground, support of 130 ~ 300kG, fixed with 4*M8*80 foundation bolts.
Page 14
INSTALLATION 2) Mounting battery module and BMS: Handle the red marked edgings of the both side of these battery modules and control module (BMS). Do not touch the connector on front. DON`T touch here Handle from here...
Page 15
INSTALLATION 3) Fix the metal bracket: Long bracket – for connecting max. 4 modules; Short bracket – for connecting max. 3 modules. Bracket can be overlap together; Make sure the bracket is fixed from the base with screws.
Page 16
INSTALLATION 4) Lock the BMS with screws:...
Page 17
INSTALLATION 5) Grounding cable connection: Grounding cable must ≥10AWG; Resistance must be less than 100mΩ.
Page 24
POWER ON 2) Power on: Double check all the previous installation procedures. 1.Switch ON Power Switch. 2.Press Start Button for ≥5S, or till buzzer rings. 3. BMS need ~30S for self-checking. *Make sure there is communication between inverter and BMS, otherwise will report external communication lost and no power output. *When the breaker is tripped off because of over current or short circuit, must wait after 10min to turn on it again, otherwise may cause the breaker damage.
Page 25
POWER ON 3) Black start: Double check all the previous installation procedures. 1.Switch ON Power Switch. 2.Press Start Button for ≥5S, or till buzzer rings. 3. BMS need ~30S for self-checking. 4. Press the Start button again for ≥10S, till the Status lighting Blue and fast flashing, then battery will black start to support inverter for 10mins to establish communication.
Page 26
POWER OFF 4) Power off: Double check all the previous installation procedures. 1. Turn off inverter or power supply on DC side. 2. Turn off the switch between PCS and battery system. 3. Turn off the “Power Switch” of the BMS.
Page 35
BEFORE YOU START • Problem is located follow above trouble shooting steps. • Switch off / cut off external power from inverter or DC side. • Switch off the BMS follow the Power OFF process. • Double-confirm D+ and D- terminal are without power.
Page 36
Replacement 1) Replace battery module: - Charge existing module to full(100%SOC), make sure the new battery module is 100%SOC as well. - Dismantle D+ and D- Power Cable, Communication Cable and Grounding Cable. - Dismantle the BMS`s fix screw of left and right side. And dismantle the fix metal brackets. - Remove the BMS, be careful there still has DC voltage on the front connector.
Page 37
Replacement 2) Replace BMS: - Dismantle D+ and D- Power Cable, Communication Cable and Grounding Cable. - Dismantle the BMS`s fix screw of left and right side. And dismantle the fix metal brackets. - Remove the BMS, be careful there still has DC voltage on the front connector. - Mount up the new BMS, fix back the brackets and screws.
Page 38
Thank You For any questions, please contact: service@pylontech.com.cn...