Commissioning; Commissioning Preparation - ABB Terra DC Wallbox Installation Manual

Hide thumbs Also See for Terra DC Wallbox:
Table of Contents

Advertisement

6

Commissioning

6.1

Commissioning preparation

Commissioning is the last phase necessary to get the Terra DC Wallbox operational. The purpose is to check the
safe functioning of the charger for its operational purpose.
An ABB certified service engineer or an ABB-trained engineer is required to perform the commissioning. During
this commissioning, the safety and the functioning of the charger will be tested. ABB Form Titled "SI-TWBCE-
001 UL CSAT Procedure DC Wallbox" (Charger System Acceptance Test) should be used for the commis-
sioning process as it contains the checklist and contact information for activation of the charger warranty.
Before the service engineer can start, the following conditions must be met:
All work described in Preparation, Construction and Placement and connection is complete with Power
available.
A local technician is present for assistance and to switch on the power.
Internet access must be available in case 4G is not functional.
A Combo compliant electric vehicle must be available for testing CCS charging.
A CHAdeMO compliant electric vehicle must be available for testing the CHAdeMO charging.
Any electric vehicle for instructing the site operator.
Commissioning is executed according to the CSAT checklist, this check list can be found in the Helios Suite Ser-
vice tool that is available to the certified commissioning engineers or their supervising ABB organization. The fol-
lowing data is required for input:
End-user Contact person (Create a contact if it doesn't exist).
Charger address (Check the site address, it will be the address the charger was shipped to).
Coordinates longitude and latitude for plots on the maps. If there are more chargers at 1 location, make
sure the coordinates are slightly different (at least 0,0001 degrees) to prevent being displayed on the
same location.
Site name if this is useful for better recognition (example: Shell petrol station Amsterdam).
External fuse of the charger.
SAT (Site Acceptance Test) date.
Location remarks (any special remarks about the site, e.g. behind a gate, no photo cameras allowed
etc.). Add a picture of the surrounding of the charger, upload the local CAF document A4 on the page of
the charger in PDF. Change Deliver status to <SAT>.
After completing the Site Acceptance Test, ABB's Network Operation Center will be triggered to perform a final
check on the connection and configuration of the charger.
Upon approval the charger will be operational and initialized for use.
2 0 2 0 - 1 2
NOTICE
Warranty : It is not allowed to move the Terra DC Wallbox, after it is commissioned. In
case the Terra DC Wallbox is moved without approval from ABB, the warranty will be
considered void. In case of relocation please contact the local ABB Service department.