From left to right for the 1-phase unit (as showed in the following picture):
PE- terminal block green/yellow, L2 - terminal block grey, L1 - terminal block grey
12. Tighten the bolts. The advised torque value is 2.9Nm.
13. After terminating the wires, make sure to adjust the terminal blocks so they are properly aligned as misa-
lignment can occur while applying proper torque to the connectors (as shown in 208/240V terminal layout
above)
2 0 2 0 - 1 2
L2 L1 208/240V 1-phase terminal
layout