Installation

The 1730CIK kit is intended to be installed at the time of
framing, and before installing the wall finish.
With the 1700 engine installed and in place, you can
proceed with the following steps to install the 1730CIK
kit.
1. Break off tabs from each corner of the fireplace's
front opening (8 tabs, 2 at each corner). Bend tabs
back and forth to break them, or cut them with tin
snips. (These tabs are only for use with kits other
than the 1730CIK)
2. File or trim any remaining sharp edges. Be careful
not to allow material to fall into the appliance.
2
3. Slide CIK frame into the opening as shown, pushing
it as far in as it will travel.
4. Screw the CIK frame to the interior of the opening (4
screws).
The fireplace and kit are now ready for wall finishing
to take place. Cement board, tile, or other wall
finishes may be completed right up to the outer
edge of the CIK frame. Do not finish past this edge,
as it will prevent barrier screen installation.