The Commissioning Process

The commissioning process is a step by step process designed to systematically check and validate all the
operational aspects of the ICAM system. The process benchmarks the performance levels tailored for each
site and generates necessary documentation for the effective management and maintenance of the system.
The steps required in a typical commissioning are listed below.
Commissioning Step
1. Pre-Commissioning (Before going to the customer
site)
2. Pre-Commissioning (Once you are on site)
3. Configuration & Thresholds
4. Test the System
5. Hand Over
www.xtralis.com
Table 2-1: Commissioning process steps
Action
Gather site information
Obtain a copy of:
Start to fill in:
ICAM Commissioning Guide
Pipe network design records
l
Pipe network installation form
l
Site plans and pipe layout plans
l
Commissioning forms
l
Any regulatory forms required
l
Check cables
l
Power up system
l
Preliminary system check
l
Configure the system
l
Set thresholds
l
Record in commissioning form:
l
Settings
o
Pipe network specifications (or attach a
o
copy of the ASPIRE Installation Data Pack)
Sampling pipe network integrity
l
Relay function
l
Detectors
l
Ancillary Devices
l
Record results
l
Performance tests
l
Complete commissioning forms and
l
attachments
Forward copies along with attachments to all
l
relevant persons