Drywall/sheetrock
Mounting tabs for
NXD Wall Mount panel
should be flush
with the outside
of the sheetrock
FIG. 56
Screw locations for conduit box attachment in a pre-wall installation
Installation of an NXD-1700VG
The NXD-1700VG can be installed either directly into the (optional) CB-TP17 or other solid surface
environment using the two different mounting options: drywall clips or solid surface screws. The
following sections describe mounting the touch panel directly into an installed pre-wall Conduit Box, a
solid surface or drywall, and optional NXA-RK17 Rack Mount Kit.
Installing the NXD-1700VG within a CB-TP17 Conduit Box
The conduit box must be mounted prior to continuing this section. Refer to the procedures in the
Pre-wall Installation of the CB-TP17 Conduit Box section on page 75 for detailed pre-wall installation
instructions. Verify that all necessary cables have been threaded through the knockouts on the conduit
box and the connections have been tested prior to installation of the NXD-1700VG.
1. Remove the magnetic faceplate/bezel (A in FIG. 57) from the main NXD unit (B in FIG. 57) by
gripping the faceplate and pulling with gentle outward force.
2. Verify the incoming RJ-45, Ethernet, and any other audio/video cables have been properly threaded
through the wiring knockouts on the left of the conduit box. Leave enough slack in the wiring to
accommodate any re-positioning of the panel.
3. Connect all data and power wiring connectors to their corresponding locations along the side of the
(un-powered) NXD touch panel.
VG-Series Modero Touch Panels
Stud
Verify the terminal end of the power cable is not connected to a power supply before plugging
in the 2-pin power connector.
The USB connectors can be from either a USB extension cable, or a wireless USB RF
transmitter.
Installation Procedures: 17" Panels
Inserted block bridges the gap
between the Conduit Box and
the notched beam
Knockouts should be located on
the left-side of the conduit box,
alongside the connectors
Stud fastening holes
Conduit Box can be
fastened to both
studs)
Use four #8 flat-head
Mounting Screws to secure
the NXD to the CB
Secure Beam to block
Depth depends on the
thickness of the Drywall
Notched stud
77