Normal Operation - Image Industries QuikLinx SW750 Operation Manual

Drawn arc stud welding power source single output
Table of Contents

Advertisement

Section 3
QuikLinx
Weld Tool (gun)
Control Connector
Shielding Gas Connector
Weld Tool (gun)
Weld Cable Connector
Standard Stud
Weld Tool (gun)
Control Connector
NOTE: This QuikLInx Stud Weld power source is unique in that it can weld both QuikLinx cable management
clips and weld standard threaded weld studs. QuikLinx clips and threaded studs require different weld tools.
Both weld tools CANNOT be connected at the same time
POWER UP
Once all the set up from section 2 has been completed the welder may be powered up.
Press (to the right or towards the 1) and momentarily hold the power switch, located on the right side of the lower portion
of the welder. The power source initiates a self test. This test lasts approximately 5 seconds. During this test routine none
of the welders's functions, including welding, will operate. This is normal. During self-test the welder will display the
current revision of software installed.
When self test ends, the welder will display the amperage and time values. The display will automatically show the values for
current and time which are saved from the last time the welder was used. Note: values are ONLY saved after a weld.

Normal Operation

15
Power Switch
Ground Cable Connector

Advertisement

Table of Contents
loading

Table of Contents