Additional Materials Required - Emerson Dosaodor-D V

Odorant injection system
Table of Contents

Advertisement

Four openings are provided for fastening, and they are
located at the endpoints of the support panel.
Two spacing brackets are part of the standard equipment
supplied with the panel. They serve for mounting the panel
leaving a space between the panel itself and the supporting wall.

Additional Materials Required

The following additional materials are required for proper
installation of the Dosaodor-D system according to Italian
standards and installations rules (not included with the order;
cable and pipe lengths depend upon the installation site).
WARNING
!
Users of Dosaodor‑D should be aware
that more detailed and specific national
standards and/or codes of practice can exist
in the CEN member and other world‑wide
countries; in particular, in the Countries
outside Europe, parts not delivered with
the product and necessary for the complete
installation (cables, connections, ...) shall
be in compliance with local regulations
concerning fire proof and products to
be installed with potential explosive
atmosphere.
a) Electrical shielded cable with CEI 20-22-marked
flameproof sheathing in the 3 x 1 size to be used for
main power supply.
b) Electrical shielded cable with CEI 20-22-marked
flameproof sheathing in the 4 x 1 size to be used for
signal transmission between the Dosaodor-D control unit
and the flow computer.
c) Electrical cable with CEI 20-22-marked flameproof
sheathing in the 1 x 4 size (yellow-green) to be used for
connecting the control unit and the pneumatic panel with
the grounding circuit.
d) Electrical shielded cable with CEI 20-22-marked
flameproof sheathing in the 3 x 1 size to be used for
connecting the absorption-type system circuit on-off
solenoid valve with the terminal black box installed on
the pneumatic panel.
e) Electrical shielded cable with CEI 20-22-marked
flameproof sheathing in the 6 x 1 size to be used for
connecting the terminal black box installed on the
pneumatic panel, with the control unit.
f) Electrical shielded cable with CEI 20-22-marked
flameproof sheathing in the 3 x 1 size to be used for
connecting the sampler junction box, installed on the
pneumatic panel, with the control unit.
g) Plastic pipe, complete with the required accessories, to
be used for protection of cable "e".
h) Plastic pipe, complete with the required accessories, to
be used for protection of cable "f".
i) Spiral sheathing in plastic material, complete with the
required accessories, to be used for protection of cable
"d".
j) Spiral sheathing in plastic material, complete with the
required accessories, to be used for protection of cable "b".
k) Spiral sheathing in plastic material, complete with the
required accessories, to be used for protection of cable "a".
l) No. 1 stop joint, with respective metal tubing stub, to
be used for sealing the cable passage between the gas
equipment facility and the facility housing the electronic
control unit - referring to pipe "g".
m) No. 1 stop joint, with respective metal tubing stub, to
be used for sealing the cable passage between the gas
equipment facility and the facility housing the electronic
control unit - referring to pipe "h".
n) Stainless steel pipe (DN 6 x 4), required for connecting
the pneumatic panel to the odorizing tank intakes and
the injection point.
o) Stainless steel pipe (DN 8 x 6), required for connecting
the pneumatic panel to the drive gas inlet / outlet points.
Note: The materials specified above are not
included with system orders as quantities are
variable and depend on the configuration and
positioning of the equipment inside the facility
structures.
To complete installation the Dosaodor-D is provided with a
kit of accessories needed for a standard system.
For standard installation and installation of the odorization
absorption type emergency system, if applicable refer to
Figure 4 on page 13.
Dosaodor-D