8
4.2: Electrical connection
1. Switch off the mains voltage (disable the fuse) or disable the
2. Connect with one of the diagrams below:
3. Verify correctness of connection.
4. Tighten the terminal screws using PH1 screwdriver.
5. If the device fully assembled, switch on the mains voltage or
6. The LED light means the device is powered.
7. Add the device to the Z-Wave network (see the next chapter).
InstallatIon
power supply.
Diagram 1: Example connection of Smart Module
Diagram 2: Example connection of Double Smart Module
enable the power supply.
2
100-240V AC
24-30V DC
S1 S2
L
N
Q
IN
B
SMART MODULE
FGS-214
2
100-240V AC
24-30V DC
S1 S2
L
N
Q2
Q1
IN
B
DOUBLE
SMART MODULE
FGS-224
1
1