Trial operation and transference to a user

1 . Before supplying power to the product, measure the grounding resistance of power terminal (3 phases: R,S,T,N/1 phase:
L,N) and outdoor unit by using a DV 500 V insulation resistance tester .
- Measured value should be 30 MΩ or above .
• Do not measure the communication terminal as the communication circuit of it can be damaged .
• Check whether the communication terminal becomes short circuit by using a circuit tester .
CAUTION
2 . Check the power voltage (L, N) before supplying power and then turn on the switch .
3 . After completing the installation, check the followings to make sure indoor unit operates without a problem .
f Strength of the ground on which indoor unit is installed
f
f Refrigerant gas leak
f
f Power supply status
f
f Insulating capacity of refrigerant pipe insulator
f
f Drainage status
f
f Connection with a circuit breaker, grounding status
f
f Status of each operation mode
f
4 . After completing the trial operation, instruct customers how to use the air conditioner .
f Turn on/off the air conditioner
f
f Operation mode and instruction of each function
f
f Cleaning the air conditioner and replacing a filter
f
• When carrying out the trial operation, operate the indoor unit individually to obtain the S-NeT data .
• After completing the installation, trial operation, and transference, advise the users to keep the user's manual and
CAUTION
installation manual .
DVM PAC Mirage_IM_05674A-00_EN.indd 35
N
AC220  V
L
ENGLISH-35
eLB
2016-04-04 오전 11:46:16

Advertisement

Table of Contents
loading

This manual is also suitable for:

Am140jnpdtk

Table of Contents