Installation
Installer and user reference guide
50
NOTICE
When the installation height of the unit needs to be increased, do NOT use stands
to only support the corners.
Stands under the unit must be at least 100 mm wide.
*
X Not allowed
O Allowed (* = preferred installation)
The height of the foundation must at least be 150 mm from the floor. In heavy
snowfall areas, this height should be increased, depending on the installation
place and condition.
The preferred installation is on a solid longitudinal foundation (steel beam frame
or concrete). The foundation must be larger than the grey marked area.
≥AB
AA
a
Minimum foundation
a Anchor point (4×)
HP
8~12
14~20
Fasten the unit in place using four foundation bolts M12. It is best to screw in the
foundation bolts until their length remains 20 mm above the foundation surface.
NOTICE
Prepare a water drainage channel around the foundation to drain waste water
from around the unit. During heating operation and when the outdoor
temperatures are negative, the drained water from the outdoor unit will freeze
up. If the water drainage is not taken care of, the area around the unit might be
very slippery.
When installed in a corrosive environment, use a nut with plastic washer (a) to
protect the nut tightening part from rust.
a
(mm)
AA
766
1076
AB
992
1302
RYYQ+RYMQ+RXYQ8~20U7Y1B
VRV IV+ heat pump
4P546228-1A – 2019.10