ABB PVS-60-TL-US Product Manual page 117

Table of Contents

Advertisement

Active Power Control (Only visible and editable with
Admin Plus privileges)
In the Active Power Control sub-menu you can config settings related
to the active power derating parameters using the following parameters
groups:
1. Active Power Curtailment
2. CEI Average VGrid Derating
3. Volt/Watt settings: P(V)
Do not change these parameters if not requested by the grid operator.
DC Settings
In the DC Settings sub-menu you can setup the parameter related to
the Input DC side:
1. VStart 1 New Value
This parameter is used to sets the Vstart activation voltage for the input
channel 1. This voltage imposes a minimum input voltage on the inverter
above which connection to the grid will be attempted.
2. VStart 2 New Value
This parameter is used to sets the Vstart activation voltage for the input
channel 2. This voltage imposes a minimum input voltage on the inverter
above which connection to the grid will be attempted.
3. VStart 3 New Value
This parameter is used to sets the Vstart activation voltage for the input
channel 3. This voltage imposes a minimum input voltage on the inverter
above which connection to the grid will be attempted.
Change the activation voltage only if really necessary and to set it to the correct value: the
photovoltaic generator sizing tool available on the ABB website will indicate whether Vstart
needs to be changed and what value have to be set.
4. Input Mode - Independ / Parallel
This settings allows you to sets the input configuration mode.
5. UV Protection Time
This section of the menu allows you to sets the time for which the in-
verter stays connected to the grid after the input voltage has dropped
below the Under Voltage limit (set at 70% of Vstart).
(60 seconds is the default setting).
- 117 -