OZONE SOLUTIONS

INSTALLATION

IMPORTANT: Keep in mind that the intake of the
pump(s) must be flooded with water (water level
above pump head) every time the pumps are started
or running, as they are not self-priming. Operating the
pumps dry will cause pump damage. Be sure to have
the pump head flooded with water anytime the pumps
are started or running.
IMPORTANT: Proper floor drainage is required to
prevent water damage in case of water leak or overflow.
Ventilation: The system should be installed in a well
ventilated area, in accordance with the environmental
specifications outlined in the individual Operation
Manuals associated with this system.

LOCATION AND MOUNTING

The ozone injection system should be installed in such
a way that all components of the system are accessible
for future maintenance. Working area required around
the system must be made available on three sides. A
minimum of 30 inches should be left for working area
around the front and both sides. The rear of the system
can be mounted against a wall or another object.
The ozone injection system is not rain or drip proof, and
therefore should be protected from rain and splashing
water. Filtered cooling inlets provide a level of protection
against dust; however for maximum longevity the
system should be located in a clean, dry area.
If the system is to be mounted in a mobile unit (such
as a trailer or movable building), mechanical shock
and vibration prevention measures need to be taken
to protect the system from damage during relocation of
the mobile unit.
Ensure that the location chosen ensures a maximum
temperature of 95°F and a maximum relative humidity
of 85%. If the parameters above cannot be maintained,
cooling and/or dehumidification equipment must be
installed. There may be exceptions to the environmental
guidelines for certain system configurations, contact
Ozone Solutions if the environmental conditions are
not as prescribed above, or otherwise in question.
8
/
WZ SERIES

MECHANICAL CONNECTIONS

Connect water piping at the fittings provided at the
edge of the skid. Ball valves at the inlet and outlet of
the system are required to allow isolation, configured
in such a way that the system can be isolated and/or
bypassed for maintenance purposes.
Process Water In
Water is supplied to the tank fitting near the front-center
of the system. The water flow switch is also installed in
this tee.
Process Water Out
Ozonated water exits the tank fitting on the right side
of the tank. If different plumbing connections are
required, adapters can be provided.
Water Sample Port
Ozone residual in the water must be checked
periodically to ensure proper operation of the ozone
injection system. This is also used to calibrate the
dissolved ozone sensor (if applicable). After the output
of the Ozone injection system, a small tee with a ball
valve should be placed in the water line. This will allow
for samples of water to be pulled to verify the dissolved
ozone level in the water.
Dissolved Ozone Monitor
Measures the dissolved ozone level exiting the contact
tank. The black cap needs to be pulled off of the tip
for it to work. Read and understand the provided
sensor instructions. The manual will inform you of the
maintenance and calibration of this probe.
Ambient Ozone Monitor
This type of monitor is to display an ozone reading
measured from the ambient air. The most common
monitor chosen is the F12 unit. This monitor can be
installed remotely from the Waterzone unit to ensure
safe conditions for employees working in the same room
as the unit, or near the ozone point of use. The output
of the monitor can be tied into the PLC system of the
Waterzone to allow automatic shut down procedures.