2. INSTALLING THE SYSTEM
2.5.4
Installing the Communication Unit on a bulkhead
Note: Install the unit with cables and connectors facing downwards.
Do as follows to mount the Communication Unit on a bulkhead:
1. Mount the Communication Unit on the bulkhead, using supplied self-tapping
screws and spaces (see the following figure).
Self-tapping screw
(Ø5×30, 4 pcs)
Note: You can install the Communication Unit without spacers.
2. Connect all cables.
Make sure that the grounding requirements are met. See chapter 4.
3. Secure the cables to the cable support using cable strips.
2.5.5
Installing the Communication Unit on a desktop
Four rubber feet make the Communication Unit well suited for desktop installation.
Simply place the Communication Unit on a desktop and connect all cables. Make sure
the grounding requirements are met. See chapter 4.
If required, fasten the Communication Unit to the desktop with four screws, as de-
scribed in section 2.5.4.
2-28
Self-tapping screw
(Ø5×60, 4 pcs)
Spacer
(6 pcs)