6. Place the retention frame onto the board and align it with the backplate standoffs.
7. Place the heatsink on the load cell assembly.
8. Install clip and tighten screws until the clip is fully installed as shown in Figure 25.

Figure 25. Heatsink Installation over the Load Cell Fixture

9. Allow the output voltage to settle (~1min) and take the voltage reading.
10. Use the load cell calibration factor to obtain the force applied by the clip.
An example measurement follows:
Initial reading:
Final reading:
Load cell calibration factor:
(129.4 – 34.5) / 1.29 = 73.6 lb
46
Preliminary Information
34.5 mV
129.4 mV
1.29 mV/lb