Mounting the display/operating unit (front mounting)

h
The protective membrane or the protective cover must be
fitted beforehand.
Drill and punch out two 22.5 mm diameter holes in the
X
front plate. The diameter is the same as is normally
required for control circuit devices.
h
Observe the following technical requirements:
• The hole spacing is 30 mm.
• The maximum thickness of the front plate must not be
more than 6 mm.
• Ensure minimum clearances (a page 11).
• In order to ensure protection to IP 65, the surface of the
mounting front must be even and smooth.
Figure 13: Drill holes for the MFD