Mounting the Product and Preparing the Connection

Danger to life due to electric shock when live cables are touched
High voltages are present on the AC and DC cables. Touching live cables results in death or
lethal injuries due to electric shock.
• Do not touch non-insulated parts or cables.
• Disconnect the AC circuit breaker and secure it against reconnection.
• Disconnect the PV array from the inverter via an external DC load-break switch (e.g. via a
PV junction including a load-break switch). Switch off and secure the DC load-break switch
against reconnection.
• Ensure that all cables to be connected are de-energized.
• Wear suitable personal protective equipment for all work on the product.
Risk of injury due to weight of product
Injuries may result if the product is lifted incorrectly or dropped while being transported or
mounted.
• Transport and lift the product carefully. Take the weight of the product into account.
• Wear suitable personal protective equipment for all work on the product.
• Transport the product using the carrying handles or hoist. Take the weight of the product
into account.
• Use all carrying handles provided during transport with carrying handles.
• Do not use the carrying handles as attachment points for hoist equipment (e.g. straps, ropes,
chains). Insert eye bolts into threads provided on top of the product to attach the hoist
system.
Procedure:
1. Mark the position for the mounting brackets.
2. Hook each mounting bracket onto the mounting rail
and insert the screw (M8x105).
Operating manual
6 Mounting and Preparing the Connection
DANGER
CAUTION
1
2
SHP-20-BE-en-12
25

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Shp 150-20Sunny highpower peak3 shp 100-20Sunny highpower peak3 shp 150-20

Table of Contents