ELECTRICAL HOOK-UP (fig. 3)
The mains cable should have a cross-
section suitable for the machine power and
should include no. 3 phase wires, no. 1
neutral cable and no. 1 earth wire.
Between the mains cable and the
compressor control panel a fused switch
near the point where the cables go into the
machine is absolutely necessary. The
switch should be at least at 1.7 m from the
ground.
The switch (A) should be easily reached by
the operator. The cables should be of the
approved type and installed with the
following grade of protection: minimum IP44
N.B. To determine the cables cross-section and the type of switch, refer to the data reported on the technical
table. Sizing according to "VDE 0100, Part 430 and 523", star-delta starter, 30° C ambient temperature and
cable length lower than 50 meters.