5.3.3 Installing the charger station on the wall
For installation on concrete, brick and wood walls, use
the included installation hardware.
For other surfaces, a suitable on-site mounting method must
be chosen.
MENNEKES recommends the installation of the charging
station at a height (up to the top edge of the enclosure) of
approximately 1.50 metres above the finished floor.
See also Fig. 13: Wall mounting.
1. Mark the mounting holes using the supplied drilling jig
and a spirit level.
2. Drill the holes in the wall with the diameter specified for
the selected installation hardware.
Wechs el ein- auf z weis paltig
Fig. 13: Wall mounting
A
Marking
Cable duct (for supply cable from above)
1
Cable duct (for supply cable from below)
2
Drilling jig
3
Wechs el ein- auf z weis paltig
3. Route the supply cable and possibly the data and
control cables to the positions specified on the frilling
jig. A cable of approx. 40 cm cable is needed for the
electrical connection inside the charging station.
4. Open the charging station (see Chapter 5.3 "Opening
the charging station" on page 13).
5. Run the supply cable and possibly the data and control
cables through the cable glands into the charging
station.
6. Secure the charging station to the wall by using dowels
and screws.
7. Check the charger for firm and secure fit.