3.
LOCATION OF INSTALLATION
Before proceeding with the installation of the equip-
ment agree the location with the client, taking into ac-
count the following points:
1.
T he base must be able to support the weight of the
unit.
2.
T he safe distances between the unit and other
equipment or structures must be strictly respected
to ensure the intake and outlet air is free to circu-
late.
3.
T he equipment must be installed by a competent
and qualified technician, in compliance with the
applicable national legislation of the country of
destination, respecting the required minimum
maintenance access spaces.
4.

POSITIONING

Before lifting the unit verify the lifting capability
of the equipment being used, taking into account
the information provided with the packaging.
When lifting insert through the unit's base holes
lifting bars (NOT PROVIDED) of sufficient length
to locate the lifting chains and safety lugs.
Position the unit in the place indicated by the
client, inserting between the unit's base and
the base support a rubber pad (minimum 10
mm thick) or anti-vibration mounts. For further
information refer to the dimensional tables.
Secure the unit and ensure it is level; check that
sufficient access is provided for hydraulic and
electrical connections.
In the case of installation where gusts of wind
may occur adequately secure the unit using ap-
propriate ties.
WARNING:
If the unit is installed in particularly windy
locations the provision of wind barriers
may be necessary to avoid malfunctions.
6
WARNING:
Lifting bars are NOT provided.
ANL / 290-650
18.03. 5719210_03

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Variable Multi Flow ANL Series and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents