Step 3: Verifying Proper Activation And Commissioning; Configuring Communication With The Battery And Energy Meter - SolarEdge StorEdge Installation Manual

Single phase inverter with hd-wave technology and setapp configuration
Hide thumbs Also See for StorEdge:
Table of Contents

Advertisement

40
  Step 3: Verifying Proper Activation and Commissioning
Information
From the Commissioning menu, select Information to view and set various system
settings, as described below.
CPU Version: The communication board firmware version
DSP 1/2 Version: The digital board firmware version
NOTE
Please have these numbers ready when you contact SolarEdge Support.
Serial Number: The inverter serial number as appears on the enclosure sticker
Error Log: Displays the last five errors, and enables resetting (clearing) the log
Warning Log: Displays the last five warnings, and enables resetting (clearing) the
log
Step 3: Verifying Proper Activation and
Commissioning
 1. Select Information and verify that the correct firmware versions are installed on each
inverter.
 2. Select Status and verify that inverter is operating and producing power (see also
Viewing System Status on page 43).
 3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
 4. Verify that the green inverter LED is steadily lit.
Your SolarEdge power harvesting system is now operational.
Configuring Communication with the Battery and
Energy Meter
This section describes how to set up communication between the inverter, Energy
Meter, and one battery over the RS485 bus.
To set up communication with the battery:
 1. Power on the system, as explained in "Connecting and Powering Systems with a DC
Disconnect Switch" on page 74.
StorEdge Single Phase Inverter with HD-Wave Technology MAN-01-00627-1.1