  Verifying the Connection
 1. Verify the ON/OFF/P switch is OFF.
 2. Verify that AC is on.
 3. Use SetApp to access the Commissioning menu screen as described in
Communication on page 38.
 4. From the Commissioning menu tap Communication. The Communication screen is
displayed.
 5. Select the following to configure the connection:
Server è LAN, Cellular or Wi-Fi
RS485- è Protocol è SolarEdge èSolarEdge Master
RS485- è Slave Detect
The system starts automatic detection of the slave inverters connected to the master
inverter. The inverter should report the correct number of slaves. If it does not, verify
the connections and terminations.
 6. To check the slave IDs and last communication time, select RS485 è Slave List.
 7. Verify the connection of the master to the monitoring platform, as described in the
next section.

Verifying the Connection

After connecting and configuring a communication option, perform the following
steps to check that the connection to the monitoring server has been successfully
established.
 1. If the Connection Unit cover is not closed, close it: Attach the Connection Unit cover
and secure it by tightening the screws with a torque of 10.3 N*m/ 7.5 lb.*ft.For
proper sealing, first tighten the corner screws and then the two central screws.
 2. Check that S_OK - Server Connected status appears in the main inverter section.
 3. Scroll down to the Communication section and check that the communication
options are as required. For more information refer to Communication Status on
StorEdge Single Phase Inverter with HD-Wave Technology MAN-01-00627-1.1