NTP- F113 Install the Bay Power and Ground
Continue with the
Step 5
Stop. You have completed this procedure.
NTP-F113 Install the Bay Power and Ground
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Warning
This product requires short-circuit (overcurrent) protection, to be provided as part of the building
installation. Install only in accordance with national and local wiring regulations. Statement 1045
Before connecting or disconnecting ground or power wires to the chassis, ensure that power is
Warning
removed from the DC circuit. To ensure that all power is OFF, locate the circuit breaker on the panel
board that services the DC circuit, switch the circuit breaker to the OFF position, and tape the switch
handle of the circuit breaker in the OFF position. Statement 140
Cisco ONS 15600 SDH Procedure Guide, R8.0
1-10
"NTP-F113 Install the Bay Power and Ground" procedure on page
This procedure explains how to install power feeds, and ground the
ONS 15600 SDH.
7/16-inch (11.1125 mm) nut driver or socket
9/64-inch (3.5719 mm) Allen wrench
Power cable, rated for at least 125-A capacity
Ground cable, rated for at least 125-A capacity
Listed pressure terminal connectors such as ring and fork types; connectors
must be suitable for the chosen cable
Wire cutters
Wire strippers
Crimp tool
Screwdriver
Nuts (4)
Two-hole power lugs, 0.625-inch hole spacing; 0.25-inch bolt holes
(Panduit LCCF2-14AZFW-E) (for underfloor-routed power cables) (16)
Under-floor power kit (800-23062-XX) (optional):
Screws (#8 x 0.75 inch) and washers (12)
Screws (#8 x 0.375 inch) and washers (8)
Power conduits (2)
Cable strain-relief brackets (2)
NTP-F109 Install the Bay Assembly, page 1-5
NTP-F111 Open and Remove the Front Door, page 1-7
Required
Onsite
None
Chapter 1 Install the Bay and Backplane Connections
1-10.
November 2009