The commissioning for SIMATIC PCS 7 BOX based on the Box PC 620 includes
the following tasks:
Commissioning/Configuration Steps
1
Configuring the PC station using the Commissioning Wizard
2
Configuring the PC using the Component Configurator
3
Creating a new PCS 7 project
4
Configuring a PCS 7 project and renaming the SIMATIC PC station
5
Setting the hardware configuration of PC stations
6
Configuring NetPro for using PDM
7
Setting time synchronization
8
Checking if the PG/PC interface is set to "PC internal"
9
Opening the operator panel of the CPU 416-2 PCI
10
Compiling and downloading the AS and OS data
11
Setting the CPU 416-2 PCI to RUN-P
The configuration tasks should be carried out in the order they appear.
Note
The commissioning and configuration tasks for the SIMATIC PCS 7 BOX
described here relate to the "single station system" configuration variant. The
special tasks for the "external engineering" and "PCS 7 network" configuration
variants are described as required. The description always relates to the "single
station system" configuration variant unless the other variants are explicitly
mentioned.