2nd Edition: June 2019 Revision 1: 17/06/2019 Model SWP L02 CE-AECO This manual covers products with Serial numbers from A2-L0001 AT00010650 SWP L02 CE-AECO Ed.02 R01 – Language: ENGLISH AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 1 6/20/2019 12:21:47 PM...
Page 2
CE certificate for SWP L02: AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 2 6/20/2019 12:21:47 PM...
Page 3
AECO certificate for SWP L02: AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 3 6/20/2019 12:21:48 PM...
Page 6
01.01 New document 02.01 Definitive (approved) edition. Option of 2 or 3 counterweights in the safety wire rope. Manufacturer updated. Certificates updated. AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 6 6/20/2019 12:21:48 PM...
HEREBY EXCLUDED TO THE MAXIMUM of the Product. The sole and exclusive remedy EXTENT PERMITTED BY APPLICABLE LAW and the entire liability of Avanti under this AND ARE EXPRESSLY DISCLAIMED BY limited warranty, shall be, at the option of AVANTI. IF, PURSUANT TO ANY APPLICABLE...
Damage to equipment or workplace situation: IMPORTANT! Useful tips for optimum None working procedure Differentiation between CE VERSION! versions and AECO version. Reference to written specification/documentation AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 8 6/20/2019 12:21:49 PM...
2.4 Terms and definitions Terms Definitions Person who has received relevant training from Avanti or a qualified instructor associated Certified technician with the intended work and who holds valid certification (current) for the task in question. Person who has received relevant training associated with using the Avanti service lift...
10 lux according to EN 50308). 60204-1 and EN 60204-32. When plugging the service lift to the power supply, ensure that supply phases are correct! AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 10 6/20/2019 12:21:49 PM...
3.2 Freight kit 3.3 The wire ropes The service lift shall be transported to destina- tion inside a box. Carefully place the cabin in the tower. Do not 1. Open the box. drag in order to avoid any damage on the 2.
Page 12
AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 12 6/20/2019 12:21:50 PM...
3.3.2 Guiding wire rope fixations The two 12mm wire ropes for guiding the lift from the top beam at Yaw platform to the tensioners at the basement are attached along the tower by means of wirefixes at platforms and additionally between platforms to ensure optimal guiding as shown below for a typical installation.
Holes in the bottom platform of the tower for wire ropes bushings and trailing power cable hole are positioned as shown in Fig. 4a and 4b. AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 14 6/20/2019 12:21:50 PM...
3.3.4 Securing the guiding 1. Drill 2 holes Ø18 x 130 mm in the concrete wire rope-ground level foundation aligned with the 2 guiding wire ropes holes of the bottom platform (see fig. Two possible options are shown depending on 4b) and install the M16 threated rods the tower integration: attach the tensioner on according to specific SWP Work Instruction.
Tension the guiding wire ropes after the first run to their final tension (7kN). AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 16 6/20/2019 12:21:51 PM...
3.4 Electrical connections 3.4.4 Power connection 1. Push the EMERGENCY STOP button of the 3.4.1 Power supply cabin operation box. 2. Check that the various stop switch cables and fall arrest device cable are connected to the The electrical connection of the traction power cabinet according to colour code.
6. Feed wire rope through cabin bushings and then through the platform floor towards the basement. Fig. 12 Fig. 13b Traction wire rope Safety wire rope AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 18 6/20/2019 12:21:52 PM...
4. Perform manual descent so that the weight of the 3.6 Securing the traction service lift is transmitted to the safety wire rope. 5. Compress the spring to 40 mm and fix with cable and safety wire rope ties. 6. Feed the safety wire rope through the compressed spring.
People have to be always attached to the anchor point when using the lift. Confirm you are properly secured before opening the door. AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 20 6/20/2019 12:21:55 PM...
Before applying the reflector tape, make sure the Inspection shall only be carried out by contact surface of the reflector bracket is clean and AVANTI or certified technicians. Refer to dry. the “AT00010648_Service Manual SWP Make sure to remove the protective film on the L02 CE EN”...
19. Dismount the cabin as necessary to be able to take the parts out of the WTG. 20. Collect all the tools and clean the working area. AVANTI Service Lift for Wind Turbines AT00010650_Installation Manual SWP L CE AECO EN E2R1.indd 22 6/20/2019 12:21:56 PM...
Need help?