4.3.9 Logic interface connection (Only for UK)

Logic interface is required by G98 and G99 standard that can be operated by a simple switch
or contactor. When the switch is closed the inverter can operated normally. When the switch
is opened, the inverter will reduce it's output power to zero within 5s.
Pin5 and Pin6 of RJ45 terminal is used for the logic interface connection.
Please follow below steps to assemble RJ45 connector.
1. Insert the network cable into the communication connection terminal of RJ45.
(As shown in figure 4.25)
Figure 4.25 RJ45 communication connection terminals
2. Use the network wire stripper to strip the insulation layer of the communication cable.
According to the standard line sequence of figure 4.26 connect the wire to the plug of
RJ45, and then use a network cable crimping tool to make it tight.
1--8
Rj45 plug
Rj45terminal
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
Switch_ input1
DRM(logic interface)
Figure 4.26 Strip the insulation layer and connect to RJ45 plug
3. Connect RJ45 to DRM (l
ogic interface
After wire connection, please refer chapter 6.5.8.1 to enable the logic interface function.
.22.
Correspondence between the cable s
and the stitch es of plug, Pin5 and Pin6
of RJ45 terminal is used for the logic
interface, other Pins are reserved.
Pin 1: Reserved; Pin 2: Reserved
Pin 3: Reserved; Pin 4: Reserved
Switch_input2
Pin 5: Switch_input1; Pin 6: Switch_input2
Pin 7: Reserved; Pin 8: Reserved
) .

5.1 Start the Inverter

To start up the Inverter, it is important that the following steps are strictly followed:
1. Switch the grid supply main Switch (AC) ON first.
2. Switch the DC switch ON. If the voltage of PV arrays are higher than start up voltage,
the inverter will turn on. The red LED power will light.
3. When both the DC and the AC sides supply to the inverter, it will be ready to generate
power. Initially, the inverter will check both its internal parameters and the parameters
of the AC grid, to ensure that they are within the acceptable limits. At the same time,
the green LED will flash and the LCD displays the information of INITIALIZING.
4. After 30-300 seconds (depending on local requirement), the inverter will start to
generate power. The green LED will be on continually and the LCD displays
GENERATING.
WARNING:
Do not touch the surface when the inverter is operating. It may be
hot and cause burns.
5.1.1 Inverter working status
When inverter working normally,there would be 5 status :
Generating:Inverter is working normally
LimByTemp: Inverter power limited by over ambient temperature.
LimByFreq: Inverter power limited by over grid frequency
LimByVg: Inverter power limited by over grid voltage
LimByVar: Inverter power limited by generating reactive power.

5.2 Stop the Inverter

To stop the Inverter, the following steps must be strictly followed:
1. Switch the Supply Main Switch (AC) OFF.
2. Wait 30 seconds. Switch the DC Switch OFF. All the LEDs of the inverter will be off in one
minute.