paused, press [2] key. If not, directly press [Enter] key.
EDIT PROGRAM
Pause Sequence=□□□□□□□□Y1
5.
Select whether short-circuit test is necessary for these two steps. If step 1
is to be tested, press [1] key. If not, directly press [Enter] key.
EDIT PROGRAM
Short Sequence=□□□□□□□□2Y
6.
Set loading time of step 1. If 2S is required, directly press [2] key on the
board. Press [Enter] key.
EDIT PROGRAM
SEQ01 On Time=2S
7.
Set unloading time of step 1. If 2S is required, directly press [2] key. Press
[Enter] key.
EDIT PROGRAM
SEQ01 Off Time=2S
8.
Set test delay time of step 1. If 1S is required, directly press [1] key. Press
[Enter] key. Tpf is delay time before measurement.
EDIT PROGRAM
SEQ01 P/F Delay Time=1S
9.
Set loading time of step 2. If 2S is required, directly press [2] key. Press
[Enter] key.
EDIT PROGRAM
SEQ02 On Time=2S
10. Set unloading time of step 2. If 2S is required, directly press [2] key. Press
[Enter] key.
EDIT PROGRAM
SEQ02 Off Time=2S
11. Set test delay time of step 2. If 1S is required, directly press [1] key. Press
[Enter] key. Tpf is delay time before measurement.
EDIT PROGRAM
SEQ02 P/F Delay Time=1S
Tpf is delay time before measurement.
12. Set conditions for stop test. COMPLETE means to stop after all tests are
completed and FAILURE means to stop in case of test error. Press [Enter]
key.
Copyright © ITECH Electronic Co., Ltd.
Function and Features
36

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the IT8800 Series and is the answer not in the manual?

This manual is also suitable for:

It8811It8812It8812bIt8812c

Table of Contents