Martin SQC2 Installation Instructions Manual page 18

Secondary cleaner
Table of Contents

Advertisement

© Martin Engineering GmbH
2. Mark the vertical and horizontal centre line of the driving drum
on the operator side of the chute wall to determine the centre
point (A, Fig. 4) of the driving drum. The vertical line must run
at a right angle with respect to the conveyor belt line.
3. Mark a position (E, Fig. 4) at a distance from 50 mm to no more
than 100 mm in the conveying direction (D, Fig. 1) from the
point at which the belt leaves the head pulley (C, Fig.4).
4. Draw a vertical line at this position (E, Fig. 4) going downwards
at a right angle to the conveyor belt.
5. Use the dimensions from Tables 2 and 3 to mark the installation
holes for the tensioner (G, Fig. 4).
6. Create the cut-out and installation holes as shown in Fig. 6/Fig.
7.
Installation SQ2, 41605, 41641
B
Fig. 6:
*The cleaner should ideally be placed in the centre of the access port.
Item
A
Blade-edge position
B
Access port
Tab. 5: Installation opening
76*
Ø16
(152)
Description
16
A
76
279
M3682UK-09/17

Advertisement

Table of Contents
loading

Table of Contents