System control standard package with piston compressors single stage and two stage
Table of Contents

Advertisement

Grasso
Refrigeration Division
3
INITIAL START UP
This chapter describes the most important steps to be taken before commisioning the GSC. These steps can also
be usefull in case changes are being made in the system.
3.1
Overview of steps to take for commissioning
1
Press "ACK" key to acknowledge all active alarms
Select ⇒ Menu "Configuration" (50)
2
Select ⇒ Menu "Control" (10)
3
Select ⇒ Menu "Operating mode" (15)
4
Select ⇒ Menu "Limit values" (20)
5
Select ⇒ Menu "Time values" (30)
6
Select ⇒ Menu "Unit options" (35)
7
Select ⇒ Menu "Configuration" (50)
8
9
Wait until the "status display" is being displayed
01.2003/0
Configure all components installed
Check/ adjust the sensor scaling
Press "Accept" to accept all changes
Check/ adjust the control settings
Check/ adjust the operating mode settings
Check/ adjust the limit value settings
Check/ adjust the time values settings
Check/ adjust the unit option settings
Press F4 key until the end without making any changes.
Next...
Press "Save" to save the settings on the EPROM
638660E_chapter3.doc
GRASSO SYSTEM CONTROL
(See chapter 3.2)
(See chapter 3.3)
(See chapter 3.4)
(See chapter 3.5)
(See chapter 3.6)
(See chapter 3.7)
(See chapter 3.8)